Our engineer team has rich experience in mould area ,more than 15 years ,also speak English very well .After we get your PO .A project engineer will be assigned follow the order request arrange design control the machining quality and lead time ,make sure all your requests has complete finished perfectly , also we will send you weekly report each week ,then even you are not in China you can know the latest project situation of each week .
We introduced precision CMM instrument. . All mold components have been passed CMM test and hold quality test report
Quality inspection is very important,therefore, we are strictly following this step
1: Mold design inspection
2: Mold Core &Cavity Steel Dimension Inspection
3: Mold Pre-Assembly Inspection
4: Mold Trial Report&Samples Inspection
5: Mold Customised testing as requested
6: Pre-mass production sample test
7: Written Quality Assurance plans for every part
8: Hourly inspections on every part with samples retained
9: Sample inspections on each batch production
10: QC control before delivery